Reference detailPoznanPoznan POL 2010
 2017
 tramSIG

Delivery and installation of signaling systems including signaling components, especially:

  • point machine TSH 106 LC (SIL3) - 86 pcs
  • point machine mechanical - 71 pcs
  • control system TSC (SIL3)
  • signal lamp
Reference detailPlzen - signaling projectsPlzen CZE 2009
 2017
 tramSIG

Delivery and installation:

  • Switch point control systems TSC (SIL 3)
  • Point machines (electro-hydraulic) - 60 pcs 
  • Point machines (mechanical) - 2 pcs
  • Radio communication system (VETRA communciation)
  • Automatic switch point heating
  • Point position indicators
  • Periodic maintenance by trained Elektroline personnel
Reference detailBrusselsBrussels BEL 2007
 2017
 tramSIG

Delivery and installation:


  • Point machines (more than 150 pcs of electro-hydraulic and over 200 of mechanical); 
  • Nonstop online support by trained Elektroline personnel



Reference detailBydgoszczBydgoszcz POL 2007
 2017
 tramSIG

Delivery and installation of signaling systems including signaling components, especially:

  • point machine TSH 106 LC (SIL3) - 40 pcs
  • mechanical point machine - over 40 pcs
Reference detailLyon TBUS line C13Lyon FRA 2012
 2014
 tbusOCL

We partly delivered material for the track and completely assembly of tbus track C13 in Lyon.


Due to very high trafic and important lines and rotes in direction of Lyon airport in this part of Lyon whole track was totally assembled at night hours.

Reference detailLinea 31Milano ITA 2012
 2014
 tramOCL

Delivery of material for TRAM line incl. diode section insulators.

Reference detailMetrocagliari, line 3 Gottardo - PoliclinicoCagliari ITA 2011
 2014
 tramOCL

Delivery of material and assembly of new double track TRAM line which is placed on the 2km-long viaduct. We also made a connection with the substation and partly adjustment at nerby depot.

Reference detailTRAM Warsaw ProjectsWarsaw POL 1999
 2014
 tramOCL
SIG

Elektroline was responsible for delivery of TRAM OCL material and signaling components for the Warszawa city. We supplied especially following products:

  • TMPK and TSC control systems (more than 200 pcs)
  • signaling lamps
  • sleeves and pole fastening
  • supporting and tensioning equipment 
  • section insulators and OCL insulators
  • GRP cantilevers and their components
  • contact wire clamps
  • tensioning mechanism and weights
  • disconnectors
  • suspensions and various OCL holders


Reference detailGeneral OCS & SIGNALING Delivery for PraguePrague CZE 1992
 2014
 tramOCL
SIG

More than 20 years cooperation (assembly & installations, material delivery and regular maintainance of our signaling devices, electro-revisions) with Prague Transport Authority. We have delivered and installed e.g.:

SIGNALING:

  • Automatic control system for switches (more than 220 pcs)
  • Automatic heating system for switchpoints

OCL SYSTEMS:

  • TRAM section insulators
  • TRAM disconnectors
  • GRP cantilevers
  • Components for cantilevers
  • contact wire clamps 
  • tensioning mechanism
Reference detailGold Coast Light RailGold Coast AUS 2012
 2013
 tramOCL

Delivery of the complete system of over head contact line material for 13km light trail track.

Reference detailAssembly of tbus switchesLa Spezia ITA 2012
 2013
 tbusOCL

Assembly and material delivery of electrical tbus switches including control systems. We also delivered other OCL material for tbus track.

Reference detailTrolejbus Karolina 1. etapa TVOstrava CZE 2012
 2013
 tbusOCL

Installation and delivery of OCL material (including electrical switches and control systems, tbus crossings, disconnectors, etc.) for TBUS line.

Reference detailFranowo DepotPoznan POL 2012
 2013
 tramSIG

In this project we are/were responsible for these deliveries and installations:

  • Automatic control system of depot
  • software & visualization for movement of vehicles within the depot
  • 42 pcs of electro-hydraulic point machines
  • 39 pcs of mechanical point machines
  • 95 pcs of resonant track circuits
  • other material and equipment: tram detection elements, signaling lamps, etc.
Reference detailRevitalisatie Nieuwe BinnenwegRotterdam NLD 2012
 2013
 tramOCL

Delivery of OCL material for tramway track and public lightning

Reference detailMalenovice - Otrokovice C440 TVMalenovice - Otrokovice CZE 2011
 2013
 tbusOCL

Installation and delivery of OCL material for TBUS line.

Items per page: 15 30 50 all 

 

 