Reference detailÚsti nad OrlicíÚsti nad Orlicí CZE 2013
 2015
 railOCL

Elektroline Inc. was responsible for delivery and assembly of overhead contact line system, remote control of sectional disconnectors, high-voltage substation, lithing in pedestrian underpass, heavy current wiring, electrical heating of switches and more.

Reference detailIbrahimli Extension and Depot KaratasGaziantep TUR 2013
 2014
 tramSIG

In scope of the project following parts were delivered and put ino operation:

  • electro-hydraulic point machines (24 pcs, with option for another 13 pcs in the future) within the depot
  • electro-hydraulic point machines (12 pcs) on intersections within the city
  • resonant track circuits
  • VETRA communication system (trackside elements) bidirectional communication system between trams and trackside systems
  • necessary hardware + software for automatic setting of tram routes within the depot
  • whole signalisation for tram drivers (traffic lights, point position indicators)
  • computer - client station with visualization of the depot and with possibility to control it
Reference detailNew TBUS DepotPilsen CZE 2013
 2014
 tbusOCL
SIG

We carried out delivery and installation of overhead contact systems for new trolleybus depot, as well as delivery and installation of automatic system for switches operation (VETRA) including all related software and computer for dispatching room. The project include e.g.:


  • 26 sets of electric switches
  • 26 sets of mechanical switches
  • 102 pcs of section insulators
  • 44 pcs of disconnectors

"Our company was pleased and fully satisfied with quality level of executed works as well as with the professional team involved in this project. Taking into consideration the above mentioned we would like to recommend Elektroline a.s. as an excellent option for executing of the OCL systems work".

Reference detailLyon TBUS line C13Lyon FRA 2012
 2014
 tbusOCL

We partly delivered material for the track and completely assembly of tbus track C13 in Lyon.


Due to very high trafic and important lines and rotes in direction of Lyon airport in this part of Lyon whole track was totally assembled at night hours.

Reference detailLinea 31Milano ITA 2012
 2014
 tramOCL

Delivery of material for TRAM line incl. diode section insulators.

Reference detailMetrocagliari, line 3 Gottardo - PoliclinicoCagliari ITA 2011
 2014
 tramOCL

Delivery of material and assembly of new double track TRAM line which is placed on the 2km-long viaduct. We also made a connection with the substation and partly adjustment at nerby depot.

Reference detailTRAM Warsaw ProjectsWarsaw POL 1999
 2014
 tramOCL
SIG

Elektroline was responsible for delivery of TRAM OCL material and signaling components for the Warszawa city. We supplied especially following products:

  • TMPK and TSC control systems (more than 200 pcs)
  • signaling lamps
  • sleeves and pole fastening
  • supporting and tensioning equipment 
  • section insulators and OCL insulators
  • GRP cantilevers and their components
  • contact wire clamps
  • tensioning mechanism and weights
  • disconnectors
  • suspensions and various OCL holders


Reference detailGeneral OCS & SIGNALING Delivery for PraguePrague CZE 1992
 2014
 tramOCL
SIG

More than 20 years cooperation (assembly & installations, material delivery and regular maintainance of our signaling devices, electro-revisions) with Prague Transport Authority. We have delivered and installed e.g.:

SIGNALING:

  • Automatic control system for switches (more than 220 pcs)
  • Automatic heating system for switchpoints

OCL SYSTEMS:

  • TRAM section insulators
  • TRAM disconnectors
  • GRP cantilevers
  • Components for cantilevers
  • contact wire clamps 
  • tensioning mechanism
Reference detailMetrocagliari, Gottardo-Settimo San PietroCagliari ITA2013 tramOCL

Delivery of OCL material for tram track.

Reference detailTramvajová trať Nové Sady - část BOlomouc CZE2013 tramOCL

Delivery of material and assembly of new tram line. We also delivered equipment for heating of switches.

Reference detailTest TrackPilsen CZE2013 railOCL

Elektroline Inc. was responsible for designing, delivery and assembly of overhead contact line system (ARCAS-EL) incl. technology for detection and signalization of traction voltage level in contact line system in range of DC 0,6 – 4 kV, AC 15 kV 16 2/3 Hz, AC 25 kV 50 Hz.  


Reference detailRenovation of MarconipleinRotterdam NLD2013 tramOCL

Delivery of OCL material for tramway track.

Reference detailGold Coast Light RailGold Coast AUS 2012
 2013
 tramOCL

Delivery of the complete system of over head contact line material for 13km light trail track.

Reference detailAssembly of tbus switchesLa Spezia ITA 2012
 2013
 tbusOCL

Assembly and material delivery of electrical tbus switches including control systems. We also delivered other OCL material for tbus track.

Reference detailTrolejbus Karolina 1. etapa TVOstrava CZE 2012
 2013
 tbusOCL

Installation and delivery of OCL material (including electrical switches and control systems, tbus crossings, disconnectors, etc.) for TBUS line.