 project
city
country
period

scope
description  
Reference detailGdynia DepotGdynia POL2007 tbusOCL

Material supply for tbus depot:

  • disconnectors including motor drives
  • remote control of disconnectors
  • novoltage status signalisation including security of maintenance workplaces for novoltage status works
Reference detailMelbourne Kew DepotMelbourne AUS2007 tramOCL

Material supply of overhead contact line line in depot

Reference detailProsmykyProsmyky CZE2007 railOCL

Elektroline a.s. was responsible for delivery and installing of material for   overhead contact line. (work place - Prosmyky )

Reference detailSenec - SladkovicovoSenec, Sladkovicovo SVK2007 railOCL

Delivery and installation:

  • Elektroline a.s. was responsible for delivery and installing of material for overhead contact line.
Reference detailAdelaideAdelaide AUS 2006
 2007
 tramOCL

Material supply for 5 km TRAM track; Cooperation on the project together with SKM company.

Reference detailLecceLecce ITA 2006
 2007
 tbusOCL

Material supply of over-head contact line - 12 km double track, including TBUS switches

Reference detailBordeauxBordeaux FRA2006 tramOCL

Assembly and installation at the project of Expansion of current tramway depot

Reference detailLyonLyon FRA2006 tramOCL

Assembly of new tramway line (8 km) LEA, crossover signalling over TRAM line

Reference detailIntersection L1/L2Montpellier FRA2006 tramOCL

Assembly of new TRAM line L2

Reference detailLyon tbus VETRA SystemLyon FRA 2005
 2006
 tbusOCL
SIG

Elektroline a.s. was responsible for delivery and installation of TBUS line,   including switches – Elektroline a.s. have installed the “VETRA” system with automatic setting of the whole trolleybus itinerary.

Reference detailCagliariCagliari ITA 2004
 2006
 tramOCL

Material supply for tram line including assmebly of OCL

Reference detailTram line SokolovskaPrague CZE2005 tramOCL

Elektroline supplied material and carried out the assembly of tram overhead contact line in total length of 1700 m double track:

  • tensioning mechanism system
  • automatic heating of switches system
  • GRP cantilevers
  • insulators and section insulators
  • supporting and tensioning equipment
  • other OCL clamps and fitting material
Reference detailTRAM line HanychovLiberec CZE 2000
 2005
 tramOCL

Elektroline company supplied material and made installation of new tram line in total length of 3000 m double track:

  • catenary system of OCL
  • automatic heating of switches system
  • TMPK switch point control systems 
  • GRP cantilevers
  • tensioning mechanism systems
  • insulators and section insulators
  • supporting and tensioning equipment
  • other OCL clamps and fitting material


Reference detailBendigoBendigo AUS2004 tramSIG

Delivery and installation:


  • Switch point control systems (2 switch points)

Maintenance:


  • Nonstop online support by trained Elektroline personnel





Reference detailMelbourneMelbourne AUS2004 tramOCL
SIG

Delivery and installation:


  • Switch point control system (1 switch point)
  • Material delivery for Overhead Contact Line
  • Nonstop online support by trained Elektroline personnel



Items per page: 15 30 50 all 

 

 

  [ WEBMAIL ][ exchange (https://remote.elektroline.cz/owa) ][ from Elektroline (https://10.0.0.2/owa) ]

english

There is a support for other languages to provide item names and other important information of minicatalogue and complete sets sections in national languages.